Scope: MEP engineering services for the three Schools for Elizabeth Board of Education. HVAC-UpgradeThe Scope included:

 

Winfield Scott #2
Provide DX cooling only air conditioning via one packaged rooftop unit (two rooftop units may be used, should the load on the roof require distribution) to serve the gymnasium space which is approximately 2700 sq.ft. Round or spiral exposed duct is installed close to the ceiling above.

 

Mable G. Holmes
Provide DX cooling only air conditioning for four (or five) classrooms via two packaged rooftop units with zones for each classroom, total classroom area totaling approximately 5000 sq.ft. The ceiling in the corridors shall be lowered to accommodate the ductwork and registers shall be wall-mounted in the classrooms.

 

Thomas Edison H.S. #87
Provide DX cooling only air conditioning for the Auditorium via one or two split a/c systems with air handlers in upper Mechanical Rooms and condensing units on adjacent roof. Existing ductwork at front of auditorium is to be reused, if possible, or new ductwork supplying existing registers to preserve architecture. Two ductless split air conditioning units may be utilized at rear of auditorium. Space is approximately 2755 sq.ft. The work included complete Electrical and HVAC design, preparation of specifications, wirings, duct layout, conduits, panelboards, load calculations and construction cost estimates. RAS is also providing construction administration services.